BreezeHost - Upstream Fiber Cutover – Maintenance details

Upstream Fiber Cutover

Completed
Scheduled for August 02, 2024 at 3:00 PM – 5:46 PM

Affects

Data Centers

Under maintenance from 3:00 PM to 5:46 PM

DFW01 - Dallas TX

Under maintenance from 3:00 PM to 5:46 PM

Updates
  • Completed
    August 02, 2024 at 5:46 PM
    Completed
    August 02, 2024 at 5:46 PM

    This maintenance has now been fully completed.

  • In progress
    August 02, 2024 at 5:38 PM
    In progress
    August 02, 2024 at 5:38 PM

    We have one more short outage as we need to move an uplink port. Please bear with us while we complete this last config change.

  • Completed
    August 02, 2024 at 4:42 PM
    Completed
    August 02, 2024 at 4:42 PM

    This maintenance has been completed successfully. Thanks for your patience.

  • Update
    August 02, 2024 at 3:31 PM
    In progress
    August 02, 2024 at 3:31 PM

    We are waiting for the NOC network engineer to arrive at the data center due to a traffic delay. Our team is on site and ready. Updates will be posted as we progress.

  • In progress
    August 02, 2024 at 3:00 PM
    In progress
    August 02, 2024 at 3:00 PM
    Maintenance is now in progress
  • Planned
    August 02, 2024 at 3:00 PM
    Planned
    August 02, 2024 at 3:00 PM

    We are planning a fiber cut over from one of our upstream providers. This is to support a new circuit coming online as we expand our bandwidth and port offerings. We are expecting a short period of downtime while the data center physically moves our cross connects to new ports.