Upstream Outage
  • Resolved
    Resolved

    This incident has been resolved. The faulty hardware has been replaced and reconfigured. Thank you all for your patience.

  • Update
    Update

    We have replaced the faulty hardware and are actively reconfiguring the system. While backup paths are in place and most services are operational, you may still experience brief interruptions as we finalize the process. We appreciate your continued patience as we work toward full resolution.

  • Update
    Update

    Our team has arrived onsite and working to remedy the faulty hardware. We have also sent requests to our upstream carriers to fix our failover. We are still working on reaching a resolution for the final remaining subnets that are experiencing issues.

  • Update
    Update

    We have identified this issue to be an issue with a locked up core switch. We have a tech en route to diagnose and repair in person. We are continuing to work on a fix for this incident.

    Most ranges have been rerouted over to backup switches and our team is working on the last few.

  • Identified
    Identified

    We have identified an outage with our primary upstream and have shifted all traffic to backup circuits. We are continuing to work on a fix for this incident.

  • Investigating
    Investigating
    We are currently investigating this incident.

Mar 2025

Charlotte NC Segra circuit upgrade
  • Completed
    March 26, 2025 at 8:34 PM
    Completed
    March 26, 2025 at 8:34 PM

    The maintenance has been completed with success. We are closing this task out now. If you have any issues, please contact support.

  • Update
    March 26, 2025 at 12:12 PM
    In progress
    March 26, 2025 at 12:12 PM

    Segra was unable to finish the upgrade last week and is wrapping this up today, March 26th - Segra and our team will be performing a "hot cut" starting at 10AM which involves swapping optics and moving connections from multiple connection points. We will advise once this maintenance is completed, but please be advised you may see intermittent drops this morning and until we are complete as a result. We will do our best to keep this down to a minimum. We will advise once it is completed.

  • Update
    March 17, 2025 at 5:32 PM
    In progress
    March 17, 2025 at 5:32 PM

    Segra NOC and field ops are still working on this upgrade and our team is continuing to remain on the call to address any issues that may arise. We will advise once the maintenance is completed

  • In progress
    March 17, 2025 at 4:00 PM
    In progress
    March 17, 2025 at 4:00 PM
    Maintenance is now in progress
  • Planned
    March 17, 2025 at 4:00 PM
    Planned
    March 17, 2025 at 4:00 PM

    At 12PM EST today, we will be upgrading our Segra circuit with Segra NOC and Field Ops teams. There may be a brief drop in connectivity, depending on your routes, but should restore automatically. We will advise once this has been completed. If you have any questions please reach out to support.

Charlotte, NC Network Issues
  • Resolved
    Resolved

    We have completed the maintenance and have tested a failure on our hardware to ensure proper VRRP and failover. We are happy to report that this is a success and as such, we are ending the maintenance. In addition, we have not see any further hardware/software issues on the new router after the failed one was replaced. At this time we are confident that we have completed this and closing the maintenance. As always, our NOC will continue monitoring our network health and advise if any changes in the network. Thank you for your patience!

  • Identified
    Identified

    We will be working on the final configurations of the replacement router starting at 3:00 PM EST. You may experience intermittent drops and issues during this time period.

    After the maintenance, this should conclude the changes for Charlotte. We will provide further updates as needed.

  • Monitoring
    Monitoring

    Malfunctioning Router has been replaced. Our networking team will be running through configurations and ensuring everything is operating as planned this evening. While we do not expect any long term outages there may be short periods of lost connections while we complete the config updates.

  • Identified
    Identified

    We have identified an issue with one of the core routers kernel panicking and rebooting.  Most customers are unaffected since we have redundantly on the new stack. However there are a few outliers that are having some issues.  We have already ordered replacement hardware to be replaced Thursday or Friday and will be working with our networking team to minimize any outages till then by migrating those affected to a different core switch.  

    As with any large scale upgrades there are bound to be a few hiccups along the way and we appreciate the patience.  Once we complete ironing out these last few issues we expect to see consistent uptimes and are already seeing much lower latency’s across the network.

    We will send updates as needed, and as we go on with the replacement.